Brampton basement inspections: what happens at each stage
The city checks a legal basement at several stages, following its mandatory inspection schedule. Book through Brampton's Building and Business Portal at least five business days ahead, with someone on site between 8am and 4pm. The city's inspection booking guidance also explains recall fees: since July 21, 2025, an ARU inspection that fails twice incurs a fee. Electrical work is inspected separately by the Electrical Safety Authority.
When is underground basement plumbing inspected?
The inspector checks drains beneath the slab before they are covered with concrete.
Can I close the walls before the rough-in inspection?
Once plumbing and HVAC rough-ins are installed, they are inspected before the walls are closed.
When are framing and fire separation inspected?
After the rough-ins pass, the city inspects structural framing. Fire separation is usually checked during the same visit.
Does insulation need an inspection before drywall?
This check follows approval of the framing and takes place before drywall installation.
Are the final building, plumbing and HVAC inspections booked together?
Book the final building, plumbing and HVAC inspections together for the same day.